Horizon Drive Active Transportation Corridor Project

Share Horizon Drive Active Transportation Corridor Project on Facebook Share Horizon Drive Active Transportation Corridor Project on Twitter Share Horizon Drive Active Transportation Corridor Project on Linkedin Email Horizon Drive Active Transportation Corridor Project link

Update Nov. 14, 2025:

The City of West Kelowna would like to provide an update on the ongoing infrastructure improvements in your area. We appreciate your patience and understanding as we work to complete this important project that will enhance active transportation infrastructure, drainage, and overall road safety.

Work completed in 2025
The following improvements have been completed this year between Olympus Way and Shale Ridge Place:

  • Sidewalk and asphalt installation
  • Stormwater improvements
  • Driveway letdowns
  • Street lighting upgrades

Weather permitting, the contractor anticipates continuing construction activities through November and into December, after which work will pause for the winter season.

Work to be completed in 2026
The next phase of the project, extending from Shale Ridge Place to the existing sidewalk south of Horizon Court, will include:

  • Sidewalk and asphalt installation
  • Stormwater improvements
  • Driveway letdowns

The remainder of the project is anticipated to be completed by spring 2026.

The project schedule required adjustments due to several contributing factors, including:

  • Unforeseen shallow utility conflicts
  • Unforeseen soil and rock conditions
  • Additional project scope and design modifications

Winter Preparation

All exposed areas will be completed and secured before winter, including asphalt, sidewalk, and driveway letdowns. This will ensure safe conditions for all forms of traffic and allow for regular winter maintenance operations.

We thank you for your continued patience and cooperation as we complete these improvements to enhance your neighbourhood.


We're upgrading Horizon Drive to enhance safety, accessibility, and connectivity by improving pedestrian and cyclist access to key neighbourhoods, schools, parks, and commercial areas.

Stay connect for project updates

Key project dates

Preparations are underway, with construction expected to begin in the coming weeks.

  • Late spring 2025: Site mobilization and early works
  • Late Fall 2025: Anticipated project completion

Timelines are subject to weather, contractor schedule/timelines and other factors. Please visit this page regularly for updates.

Project scope

What work is being done?

The road upgrades will include:

  • 1.1 kilometres of new sidewalks, curbs, and gutters along the west side of Horizon Drive.
  • 2.2 kilometres of new dedicated bike lanes on both sides of Horizon Drive for safer cycling.
  • Upgraded street lighting, storm improvements and ditching.
  • New road markings and signage to enhance visibility and safety for all users.

What to expect during construction

Construction activities may result in occasional noise, dust, dirt, and vibrations. Work outside of typical construction hours may be required on a temporary basis. Driveway accesses will be maintained, with only minor interruptions to allow for the movement of crews and equipment.

The City of West Kelowna will have a comprehensive traffic management plan for this project, and we will communicate the plan to the public in advance of any traffic pattern changes.

Key construction activities include:

  • Mobilization of crews, equipment, and materials to the site.
  • Completion of stormwater and road upgrades, as well as the installation of bike lanes and streetlights.
  • Continuous access for pedestrians and cyclists.
  • Coordination by the contractor to ensure residents within the work area retain access to their homes.
  • Placement of signage and reader boards along the the work zone to help regulate traffic speeds.

Please note that access for transit and emergency vehicles will be maintained throughout all phases of construction.


Ask us

Have questions about the project? Ask them below!

Update Nov. 14, 2025:

The City of West Kelowna would like to provide an update on the ongoing infrastructure improvements in your area. We appreciate your patience and understanding as we work to complete this important project that will enhance active transportation infrastructure, drainage, and overall road safety.

Work completed in 2025
The following improvements have been completed this year between Olympus Way and Shale Ridge Place:

  • Sidewalk and asphalt installation
  • Stormwater improvements
  • Driveway letdowns
  • Street lighting upgrades

Weather permitting, the contractor anticipates continuing construction activities through November and into December, after which work will pause for the winter season.

Work to be completed in 2026
The next phase of the project, extending from Shale Ridge Place to the existing sidewalk south of Horizon Court, will include:

  • Sidewalk and asphalt installation
  • Stormwater improvements
  • Driveway letdowns

The remainder of the project is anticipated to be completed by spring 2026.

The project schedule required adjustments due to several contributing factors, including:

  • Unforeseen shallow utility conflicts
  • Unforeseen soil and rock conditions
  • Additional project scope and design modifications

Winter Preparation

All exposed areas will be completed and secured before winter, including asphalt, sidewalk, and driveway letdowns. This will ensure safe conditions for all forms of traffic and allow for regular winter maintenance operations.

We thank you for your continued patience and cooperation as we complete these improvements to enhance your neighbourhood.


We're upgrading Horizon Drive to enhance safety, accessibility, and connectivity by improving pedestrian and cyclist access to key neighbourhoods, schools, parks, and commercial areas.

Stay connect for project updates

Key project dates

Preparations are underway, with construction expected to begin in the coming weeks.

  • Late spring 2025: Site mobilization and early works
  • Late Fall 2025: Anticipated project completion

Timelines are subject to weather, contractor schedule/timelines and other factors. Please visit this page regularly for updates.

Project scope

What work is being done?

The road upgrades will include:

  • 1.1 kilometres of new sidewalks, curbs, and gutters along the west side of Horizon Drive.
  • 2.2 kilometres of new dedicated bike lanes on both sides of Horizon Drive for safer cycling.
  • Upgraded street lighting, storm improvements and ditching.
  • New road markings and signage to enhance visibility and safety for all users.

What to expect during construction

Construction activities may result in occasional noise, dust, dirt, and vibrations. Work outside of typical construction hours may be required on a temporary basis. Driveway accesses will be maintained, with only minor interruptions to allow for the movement of crews and equipment.

The City of West Kelowna will have a comprehensive traffic management plan for this project, and we will communicate the plan to the public in advance of any traffic pattern changes.

Key construction activities include:

  • Mobilization of crews, equipment, and materials to the site.
  • Completion of stormwater and road upgrades, as well as the installation of bike lanes and streetlights.
  • Continuous access for pedestrians and cyclists.
  • Coordination by the contractor to ensure residents within the work area retain access to their homes.
  • Placement of signage and reader boards along the the work zone to help regulate traffic speeds.

Please note that access for transit and emergency vehicles will be maintained throughout all phases of construction.


Ask us

Have questions about the project? Ask them below!

  • Project Update 2 - Wednesday, June 25, 2025

    Share Project Update 2 - Wednesday, June 25, 2025 on Facebook Share Project Update 2 - Wednesday, June 25, 2025 on Twitter Share Project Update 2 - Wednesday, June 25, 2025 on Linkedin Email Project Update 2 - Wednesday, June 25, 2025 link
    supporting image

    Date of Issue: Wednesday, June 25, 2025

    The City of West Kelowna is upgrading the Horizon Drive Active Transportation Corridor to improve safety, accessibility, and connectivity. This active transportation corridor project will enhance pedestrian and cyclist access between key neighbourhoods, schools, parks, and commercial areas.

    Construction is scheduled to begin on Wednesday, July 2, and will continue throughout the summer, with anticipated completion in fall 2025. Crews will work weekdays from 7:00 a.m. to 5:00 p.m., with the possibility of occasional weekend work.

    Thanks to the B.C. Ministry of Transportation and Transit for providing funding of up to $500,000 through the B.C. Active Transportation Infrastructure Grants Program towards the Horizon Drive Active Transportation Corridor Project.

    What work is being done

    The road upgrades will include:

    • 1.1 kilometres of new sidewalks, curbs, and gutters along the west side of Horizon Drive.
    • 2.2 kilometres of new dedicated bike lanes on both sides of Horizon Drive for safer cycling.
    • Upgraded street lighting, storm improvements and ditching.
    • New road markings and signage to enhance visibility and safety for all users.

    Please note the construction schedule is subject to weather conditions, contractor schedule changes and other factors.

    Motorists are advised to drive with caution, follow all posted speed limits and expect minor delays when travelling through the work area.

    Pedestrian access will be maintained throughout construction and cyclists are encouraged to dismount through the construction zone. Access for emergency vehicles and school bus service will be maintained at all times. The contractor will coordinate local access for residents living within the work area to ensure continued access to their homes.

    The City of West Kelowna thanks residents and businesses for their patience and understanding while crews work to create an active transportation corridor along Horizon Drive.

    Project map

    Stay connected for project updates:

  • Project Update 1 - Wednesday, June 4, 2025

    Share Project Update 1 - Wednesday, June 4, 2025 on Facebook Share Project Update 1 - Wednesday, June 4, 2025 on Twitter Share Project Update 1 - Wednesday, June 4, 2025 on Linkedin Email Project Update 1 - Wednesday, June 4, 2025 link
    supporting image

    Date of Issue: Wednesday, June 4, 2025

    This summer, the City of West Kelowna is investing in key infrastructure upgrades, including sidewalk extensions, active transportation and intersection improvements, and essential roadway and drainage enhancements throughout the community.

    We’re excited to share a preview of major transportation projects that will begin in the coming weeks.

    Stay informed on road closures and project updates

    For the latest information on closures, detours, and project progress, visitOurWK.ca or subscribe to have news and alerts delivered directly to your inbox atwestkelownacity.ca/subscribe(External link), or follow us for updates on Facebook, Instagram and X.

    Read the full project update here(External link).

  • Project Updates

    Share Project Updates on Facebook Share Project Updates on Twitter Share Project Updates on Linkedin Email Project Updates link
    supporting image

    Stay tuned for updates throughout the project!

Page last updated: 14 Nov 2025, 02:33 PM