Horizon Drive Active Transportation Corridor Project

Share Horizon Drive Active Transportation Corridor Project on Facebook Share Horizon Drive Active Transportation Corridor Project on X (formerly Twitter) Share Horizon Drive Active Transportation Corridor Project on Linkedin Email Horizon Drive Active Transportation Corridor Project link

PROJECT UPDATE AND TIMELINE

The City of West Kelowna has retained a civil construction contractor to complete the remaining construction works; this work is tentatively scheduled to start as early as the week of Sept. 14, 2026.

Prior to awarding the project to a new construction contractor, the City took over coordination of the project following a previous contractor default.

Capital and Engineering departments presented a direct award recommendation for paving at the Sept. 8 council meeting. The proposed award for asphalt work represents a significant milestone toward project completion.

Emil Anderson Construction (EAC) Inc. has been awarded the contract for paving for the remainder of project.

Residents can anticipate asphalt paving to take place in mid-October, with landscaping remediation following paving. Residents should begin seeing visible progress in the coming weeks.

Overall, project completion is currently anticipated for November 2026.

REMAINING WORK FOR 2026

The next phase of the project, extending from Shale Ridge Place to the existing sidewalk south of Horizon Court, will include:

  • Road widening and culvert extensions
  • Street lighting
  • Asphalt paving
  • Line painting
  • Landscaping
  • Frontage restoration
  • Completion of outstanding deficiencies

Landscaping activities are currently underway as topsoil placed along the front lawns on Horizon Drive is part of the planned lawn restoration. The City plans to hydro-seed these areas in the fall, which will allow the grass seeds to germinate and establish in the new topsoil.

WORK COMPLETED IN 2025

The following improvements have been completed this year between Olympus Way and Shale Ridge Place:

  • Sidewalk and asphalt installation
  • Stormwater improvements
  • Driveway letdowns
  • Street lighting upgrades

The City of West Kelowna thanks residents and businesses for their patience and understanding while the work is completed on the project. The project has faced unexpected and unacceptable delays under the original contractor who eventually defaulted on the contract. Following the default, the City was required to take the necessary contractual and procurement steps to assume construction coordination and advance the remaining work toward completion. The City recognizes this project has taken a year longer than anticipated and apologizes for the long disruption for residents.


Stay connected for project updates

Project scope

What work is being done?

The road upgrades will include:

  • 1.1 kilometres of new sidewalks, curbs, and gutters along the west side of Horizon Drive.
  • 2.2 kilometres of new dedicated bike lanes on both sides of Horizon Drive for safer cycling.
  • Upgraded street lighting, storm improvements and ditching.
  • New road markings and signage to enhance visibility and safety for all users.

What to expect during construction

Construction activities may result in occasional noise, dust, dirt, and vibrations. Work outside of typical construction hours may be required on a temporary basis. Driveway accesses will be maintained, with only minor interruptions to allow for the movement of crews and equipment.

The City of West Kelowna will have a comprehensive traffic management plan for this project, and we will communicate the plan to the public in advance of any traffic pattern changes.

Key construction activities include:

  • Mobilization of crews, equipment, and materials to the site.
  • Completion of stormwater and road upgrades, as well as the installation of bike lanes and streetlights.
  • Continuous access for pedestrians and cyclists.
  • Coordination by the contractor to ensure residents within the work area retain access to their homes.
  • Placement of signage and reader boards along the the work zone to help regulate traffic speeds.

Please note that access for transit and emergency vehicles will be maintained throughout all phases of construction.

Ask us

Have questions about the project? Ask them below!

PROJECT UPDATE AND TIMELINE

The City of West Kelowna has retained a civil construction contractor to complete the remaining construction works; this work is tentatively scheduled to start as early as the week of Sept. 14, 2026.

Prior to awarding the project to a new construction contractor, the City took over coordination of the project following a previous contractor default.

Capital and Engineering departments presented a direct award recommendation for paving at the Sept. 8 council meeting. The proposed award for asphalt work represents a significant milestone toward project completion.

Emil Anderson Construction (EAC) Inc. has been awarded the contract for paving for the remainder of project.

Residents can anticipate asphalt paving to take place in mid-October, with landscaping remediation following paving. Residents should begin seeing visible progress in the coming weeks.

Overall, project completion is currently anticipated for November 2026.

REMAINING WORK FOR 2026

The next phase of the project, extending from Shale Ridge Place to the existing sidewalk south of Horizon Court, will include:

  • Road widening and culvert extensions
  • Street lighting
  • Asphalt paving
  • Line painting
  • Landscaping
  • Frontage restoration
  • Completion of outstanding deficiencies

Landscaping activities are currently underway as topsoil placed along the front lawns on Horizon Drive is part of the planned lawn restoration. The City plans to hydro-seed these areas in the fall, which will allow the grass seeds to germinate and establish in the new topsoil.

WORK COMPLETED IN 2025

The following improvements have been completed this year between Olympus Way and Shale Ridge Place:

  • Sidewalk and asphalt installation
  • Stormwater improvements
  • Driveway letdowns
  • Street lighting upgrades

The City of West Kelowna thanks residents and businesses for their patience and understanding while the work is completed on the project. The project has faced unexpected and unacceptable delays under the original contractor who eventually defaulted on the contract. Following the default, the City was required to take the necessary contractual and procurement steps to assume construction coordination and advance the remaining work toward completion. The City recognizes this project has taken a year longer than anticipated and apologizes for the long disruption for residents.


Stay connected for project updates

Project scope

What work is being done?

The road upgrades will include:

  • 1.1 kilometres of new sidewalks, curbs, and gutters along the west side of Horizon Drive.
  • 2.2 kilometres of new dedicated bike lanes on both sides of Horizon Drive for safer cycling.
  • Upgraded street lighting, storm improvements and ditching.
  • New road markings and signage to enhance visibility and safety for all users.

What to expect during construction

Construction activities may result in occasional noise, dust, dirt, and vibrations. Work outside of typical construction hours may be required on a temporary basis. Driveway accesses will be maintained, with only minor interruptions to allow for the movement of crews and equipment.

The City of West Kelowna will have a comprehensive traffic management plan for this project, and we will communicate the plan to the public in advance of any traffic pattern changes.

Key construction activities include:

  • Mobilization of crews, equipment, and materials to the site.
  • Completion of stormwater and road upgrades, as well as the installation of bike lanes and streetlights.
  • Continuous access for pedestrians and cyclists.
  • Coordination by the contractor to ensure residents within the work area retain access to their homes.
  • Placement of signage and reader boards along the the work zone to help regulate traffic speeds.

Please note that access for transit and emergency vehicles will be maintained throughout all phases of construction.

Ask us

Have questions about the project? Ask them below!

  • Project Update 3 - Tuesday, Sept. 8, 2026.

    Share Project Update 3 - Tuesday, Sept. 8, 2026. on Facebook Share Project Update 3 - Tuesday, Sept. 8, 2026. on X (formerly Twitter) Share Project Update 3 - Tuesday, Sept. 8, 2026. on Linkedin Email Project Update 3 - Tuesday, Sept. 8, 2026. link
    supporting image

    The City of West Kelowna is in the process of retaining a civil construction contractor to complete the remaining construction works, this work is tentatively scheduled to start as early as the week of Sept. 14, 2026.

    The City has taken over coordination of the project following the contractor default and has developed procurement packages for the remaining scopes of work.

    Capital and Engineering departments presented a direct award recommendation for paving at the Sept. 8 council meeting. The proposed award of the asphalt works represents a significant milestone toward project completion.

    Emil Anderson Construction (EAC) Inc. has been awarded the contract for paving for the remainder of project.

    Residents can anticipate asphalt paving to take place in mid-October, with landscaping remediation works following paving. Residents should begin seeing visible progress in the coming weeks.

    Overall, project completion is currently anticipated for November 2026.

    REMAINING WORK FOR 2026

    The next phase of the project, extending from Shale Ridge Place to the existing sidewalk south of Horizon Court, will include:

    • Road widening and culvert extensions
    • Street lighting
    • Asphalt paving
    • Line painting
    • Landscaping
    • Frontage restoration
    • Completion of outstanding deficiencies

    Landscaping activities are currently underway as topsoil placed along the front lawns on Horizon Drive is part of the planned lawn restoration. The City plans to hydro-seed these areas in the fall, which will allow the grass seeds to germinate and establish in the new topsoil.

    The City of West Kelowna is in the process of retaining a civil construction contractor to complete the remaining construction works, this work is tentatively scheduled to start as early as the week of Sept. 14, 2026.

    The City has taken over coordination of the project following the contractor default and has developed procurement packages for the remaining scopes of work.

    Capital and Engineering departments presented a direct award recommendation for paving at the Sept. 8 council meeting. The proposed award of the asphalt works represents a significant milestone toward project completion.

    Emil Anderson Construction (EAC) Inc. has been awarded the contract for paving for the remainder of project.

    Residents can anticipate asphalt paving to take place in mid-October, with landscaping remediation works following paving. Residents should begin seeing visible progress in the coming weeks.

    Overall, project completion is currently anticipated for November 2026.

    REMAINING WORK FOR 2026

    The next phase of the project, extending from Shale Ridge Place to the existing sidewalk south of Horizon Court, will include:

    • Road widening and culvert extensions
    • Street lighting
    • Asphalt paving
    • Line painting
    • Landscaping
    • Frontage restoration
    • Completion of outstanding deficiencies

    Landscaping activities are currently underway as topsoil placed along the front lawns on Horizon Drive is part of the planned lawn restoration. The City plans to hydro-seed these areas in the fall, which will allow the grass seeds to germinate and establish in the new topsoil.

  • Project Update 2 - Wednesday, June 25, 2025

    Share Project Update 2 - Wednesday, June 25, 2025 on Facebook Share Project Update 2 - Wednesday, June 25, 2025 on X (formerly Twitter) Share Project Update 2 - Wednesday, June 25, 2025 on Linkedin Email Project Update 2 - Wednesday, June 25, 2025 link
    supporting image

    Date of Issue: Wednesday, June 25, 2025

    The City of West Kelowna is upgrading the Horizon Drive Active Transportation Corridor to improve safety, accessibility, and connectivity. This active transportation corridor project will enhance pedestrian and cyclist access between key neighbourhoods, schools, parks, and commercial areas.

    Construction is scheduled to begin on Wednesday, July 2, and will continue throughout the summer, with anticipated completion in fall 2025. Crews will work weekdays from 7:00 a.m. to 5:00 p.m., with the possibility of occasional weekend work.

    Thanks to the B.C. Ministry of Transportation and Transit for providing funding of up to $500,000 through the B.C. Active Transportation Infrastructure Grants Program towards the Horizon Drive Active Transportation Corridor Project.

    What work is being done

    The road upgrades will include:

    • 1.1 kilometres of new sidewalks, curbs, and gutters along the west side of Horizon Drive.
    • 2.2 kilometres of new dedicated bike lanes on both sides of Horizon Drive for safer cycling.
    • Upgraded street lighting, storm improvements and ditching.
    • New road markings and signage to enhance visibility and safety for all users.

    Please note the construction schedule is subject to weather conditions, contractor schedule changes and other factors.

    Motorists are advised to drive with caution, follow all posted speed limits and expect minor delays when travelling through the work area.

    Pedestrian access will be maintained throughout construction and cyclists are encouraged to dismount through the construction zone. Access for emergency vehicles and school bus service will be maintained at all times. The contractor will coordinate local access for residents living within the work area to ensure continued access to their homes.

    The City of West Kelowna thanks residents and businesses for their patience and understanding while crews work to create an active transportation corridor along Horizon Drive.

    Project map

    Stay connected for project updates:

    Date of Issue: Wednesday, June 25, 2025

    The City of West Kelowna is upgrading the Horizon Drive Active Transportation Corridor to improve safety, accessibility, and connectivity. This active transportation corridor project will enhance pedestrian and cyclist access between key neighbourhoods, schools, parks, and commercial areas.

    Construction is scheduled to begin on Wednesday, July 2, and will continue throughout the summer, with anticipated completion in fall 2025. Crews will work weekdays from 7:00 a.m. to 5:00 p.m., with the possibility of occasional weekend work.

    Thanks to the B.C. Ministry of Transportation and Transit for providing funding of up to $500,000 through the B.C. Active Transportation Infrastructure Grants Program towards the Horizon Drive Active Transportation Corridor Project.

    What work is being done

    The road upgrades will include:

    • 1.1 kilometres of new sidewalks, curbs, and gutters along the west side of Horizon Drive.
    • 2.2 kilometres of new dedicated bike lanes on both sides of Horizon Drive for safer cycling.
    • Upgraded street lighting, storm improvements and ditching.
    • New road markings and signage to enhance visibility and safety for all users.

    Please note the construction schedule is subject to weather conditions, contractor schedule changes and other factors.

    Motorists are advised to drive with caution, follow all posted speed limits and expect minor delays when travelling through the work area.

    Pedestrian access will be maintained throughout construction and cyclists are encouraged to dismount through the construction zone. Access for emergency vehicles and school bus service will be maintained at all times. The contractor will coordinate local access for residents living within the work area to ensure continued access to their homes.

    The City of West Kelowna thanks residents and businesses for their patience and understanding while crews work to create an active transportation corridor along Horizon Drive.

    Project map

    Stay connected for project updates:

  • Project Update 1 - Wednesday, June 4, 2025

    Share Project Update 1 - Wednesday, June 4, 2025 on Facebook Share Project Update 1 - Wednesday, June 4, 2025 on X (formerly Twitter) Share Project Update 1 - Wednesday, June 4, 2025 on Linkedin Email Project Update 1 - Wednesday, June 4, 2025 link
    supporting image

    Date of Issue: Wednesday, June 4, 2025

    This summer, the City of West Kelowna is investing in key infrastructure upgrades, including sidewalk extensions, active transportation and intersection improvements, and essential roadway and drainage enhancements throughout the community.

    We’re excited to share a preview of major transportation projects that will begin in the coming weeks.

    Stay informed on road closures and project updates

    For the latest information on closures, detours, and project progress, visitOurWK.ca or subscribe to have news and alerts delivered directly to your inbox atwestkelownacity.ca/subscribe(External link), or follow us for updates on Facebook, Instagram and X.

    Read the full project update here(External link).

    Date of Issue: Wednesday, June 4, 2025

    This summer, the City of West Kelowna is investing in key infrastructure upgrades, including sidewalk extensions, active transportation and intersection improvements, and essential roadway and drainage enhancements throughout the community.

    We’re excited to share a preview of major transportation projects that will begin in the coming weeks.

    Stay informed on road closures and project updates

    For the latest information on closures, detours, and project progress, visitOurWK.ca or subscribe to have news and alerts delivered directly to your inbox atwestkelownacity.ca/subscribe(External link), or follow us for updates on Facebook, Instagram and X.

    Read the full project update here(External link).

  • Project Updates

    Share Project Updates on Facebook Share Project Updates on X (formerly Twitter) Share Project Updates on Linkedin Email Project Updates link
    supporting image

    Stay tuned for updates throughout the project!