Shannon Lake Road Active Transportation Corridor Project
PROJECT UPDATE
Road paving work begins - Bulk Water Station temporarily closed
Road paving work is expected to occur on Friday, Sept. 6 and Tuesday, Sept. 10. During this time, the Bulk Water Station will temporarily close to accommodate paving crews and equipment. Read the traffic advisory for more information.
Residents are encouraged to plan their water needs in advance and use the filling station prior to the temporary closure. Watermain flushing will be temporarily paused during the closure of the filling station.
The detour on Shannon Lake Road via Shannon Way to Woodstock Drive to Shannon Place and Shannon Ridge Drive will remain in place as crews work to complete construction of the roundabout at the Asquith Road intersection. The intermittent single-lane alternating traffic pattern on weekdays from 7:00 a.m. to 6:00 p.m. on Shannon Lake Road from Shannon Ridge Drive to Swite Road will continue for Phase 3.
We are enhancing road safety and creating an active transportation corridor for our community along Shannon Lake Road!
Construction of a new multi-use pathway and road upgrades on Shannon Lake Road will enhance safety and create new active transportation and healthy living opportunities.
The $5.2 million project will be constructed in two sections and all work is anticipated to be complete in summer 2025. Partial funding of up to $500,000 is being provided under the B.C. Active Transportation Infrastructure Grant Program. Thank you to the Government of British Columbia!
Key project dates
- Spring 2024: Site mobilization and early works
- Summer 2025: Project complete
Timelines are subject to weather, contractor timelines and other factors. Please visit this page regularly for updates.
The project is being constructed in two sections, which will consist of:
Section 1
Section 1 will be completed in three phases:
- Phase 1: Road improvements from Kinsmen Park (lower field) to Asquith Road
- Phase 2: Construction of a roundabout at the Asquith and Shannon Lake Road intersection
- Phase 3: Road improvements from Asquith Road to Swite Road
Section 1 project scope: What work is being done?
- 1.7-kilometre (850-metres each side of roadway) multi-use pathway on both sides of the roadway from Kinsmen Park (lower field) to Swite Road
- Roundabout at Asquith Road and Shannon Lake Road intersection
- 900 metres of road upgrades which includes concrete curbs and paving
- Pedestrian activated crosswalks at Kinsmen Park (lower field), Shannon Way, and Shannon Ridge Drive
- 850 metres of street lighting on both sides of the roadway from Kinsmen Park (lower field) to Swite Road
- Stormwater upgrades
- Landscaped boulevards
Section 2
Section 2 of the project is scheduled for spring 2025, and will see additional asphalt sidewalks added from Golf Course Drive to the existing sidewalk at 2649 Shannon Lake Road.
Section 2 project scope: What work is being done?
- 400 metres of 1.8-metre-wide asphalt sidewalk and bike lanes between Golf Course Drive to existing sidewalk at 2649 Shannon Lake Road
- 400 metres of streetlighting
What to expect during construction
Construction may cause occasional noise, dust, dirt and vibrations. Work outside of typical construction hours may be required temporarily. Driveway accesses will be maintained with minor interruptions for moving crews and equipment:
- Crews will mobilize to the site and stage equipment and materials
- Crews will complete stormwater and road upgrade work, install bike lanes and streetlights
- Pedestrian and cyclist access will be maintained
- The contractor will coordinate local access for residents living within the work area to ensure continued access to their homes
- Access to Kinsmen Park will be maintained
- Signs and reader boards will be placed along the detour route to help regulate speeds
Please note that during all phases of construction, access for transit and emergency vehicles will be maintained.
Ask us
Have questions about the project? Ask them below!
Ask a question
Do you have questions about the project? Ask them here, and we'll respond to your question in 2-3 business days.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends