Shannon Lake Road Active Transportation Corridor Project
Share Shannon Lake Road Active Transportation Corridor Project on FacebookShare Shannon Lake Road Active Transportation Corridor Project on TwitterShare Shannon Lake Road Active Transportation Corridor Project on LinkedinEmail Shannon Lake Road Active Transportation Corridor Project link
Enhancing road safety and creating an active transportation corridor for our community along Shannon Lake Road
Construction of a new multi-use pathway and road upgrades on Shannon Lake Road will enhance safety and create new active transportation and healthy living opportunities.
The $5.2 million project will be constructed in two sections and all work is anticipated to be complete in summer 2025. Partial funding of up to $500,000 is being provided under the B.C. Active Transportation Infrastructure Grant Program. Thank you to the Government of British Columbia!
Key project dates
Spring 2024: Site mobilization and early works
Summer 2025: Project complete
Timelines are subject to weather, contractor timelines and other factors. Please visit this page regularly for updates.
The project is being constructed in two sections, which will consist of:
Section 1
Section 1 will be completed in three phases:
Phase 1: Road improvements from Kinsmen Park (lower field) to Asquith Road
Phase 2: Construction of a roundabout at the Asquith and Shannon Lake Road intersection
Phase 3: Road improvements from Asquith Road to Swite Road
Section 1 project scope: What work is being done?
1.7-kilometre (850-metres each side of roadway) multi-use pathway on both sides of the roadway from Kinsmen Park (lower field) to Swite Road
Roundabout at Asquith Road and Shannon Lake Road intersection
900 metres of road upgrades which includes concrete curbs and paving
Pedestrian activated crosswalks at Kinsmen Park (lower field), Shannon Way, and Shannon Ridge Drive
850 metres of street lighting on both sides of the roadway from Kinsmen Park (lower field) to Swite Road
Stormwater upgrades
Landscaped boulevards
Section 2
Section 2 of the project is scheduled for spring 2025, and will see additional asphalt sidewalks added from Golf Course Drive to the existing sidewalk at 2649 Shannon Lake Road.
Section 2project scope: What work is being done?
400 metres of 1.8-metre-wide asphalt sidewalk and bike lanes between Golf Course Drive to existing sidewalk at 2649 Shannon Lake Road
400 metres of streetlighting
What to expect during construction
Construction may cause occasional noise, dust, dirt and vibrations. Work outside of typical construction hours may be required temporarily. Driveway accesses will be maintained with minor interruptions for moving crews and equipment:
Crews will mobilize to the site and stage equipment and materials
Crews will complete stormwater and road upgrade work, install bike lanes and streetlights
Pedestrian and cyclist access will be maintained
The contractor will coordinate local access for residents living within the work area to ensure continued access to their homes
Access to Kinsmen Park will be maintained
Signs and reader boards will be placed along the detour route to help regulate speeds
Please note that during all phases of construction, access for transit and emergency vehicles will be maintained.
Ask us
Have questions about the project? Ask them below!
Enhancing road safety and creating an active transportation corridor for our community along Shannon Lake Road
Construction of a new multi-use pathway and road upgrades on Shannon Lake Road will enhance safety and create new active transportation and healthy living opportunities.
The $5.2 million project will be constructed in two sections and all work is anticipated to be complete in summer 2025. Partial funding of up to $500,000 is being provided under the B.C. Active Transportation Infrastructure Grant Program. Thank you to the Government of British Columbia!
Key project dates
Spring 2024: Site mobilization and early works
Summer 2025: Project complete
Timelines are subject to weather, contractor timelines and other factors. Please visit this page regularly for updates.
The project is being constructed in two sections, which will consist of:
Section 1
Section 1 will be completed in three phases:
Phase 1: Road improvements from Kinsmen Park (lower field) to Asquith Road
Phase 2: Construction of a roundabout at the Asquith and Shannon Lake Road intersection
Phase 3: Road improvements from Asquith Road to Swite Road
Section 1 project scope: What work is being done?
1.7-kilometre (850-metres each side of roadway) multi-use pathway on both sides of the roadway from Kinsmen Park (lower field) to Swite Road
Roundabout at Asquith Road and Shannon Lake Road intersection
900 metres of road upgrades which includes concrete curbs and paving
Pedestrian activated crosswalks at Kinsmen Park (lower field), Shannon Way, and Shannon Ridge Drive
850 metres of street lighting on both sides of the roadway from Kinsmen Park (lower field) to Swite Road
Stormwater upgrades
Landscaped boulevards
Section 2
Section 2 of the project is scheduled for spring 2025, and will see additional asphalt sidewalks added from Golf Course Drive to the existing sidewalk at 2649 Shannon Lake Road.
Section 2project scope: What work is being done?
400 metres of 1.8-metre-wide asphalt sidewalk and bike lanes between Golf Course Drive to existing sidewalk at 2649 Shannon Lake Road
400 metres of streetlighting
What to expect during construction
Construction may cause occasional noise, dust, dirt and vibrations. Work outside of typical construction hours may be required temporarily. Driveway accesses will be maintained with minor interruptions for moving crews and equipment:
Crews will mobilize to the site and stage equipment and materials
Crews will complete stormwater and road upgrade work, install bike lanes and streetlights
Pedestrian and cyclist access will be maintained
The contractor will coordinate local access for residents living within the work area to ensure continued access to their homes
Access to Kinsmen Park will be maintained
Signs and reader boards will be placed along the detour route to help regulate speeds
Please note that during all phases of construction, access for transit and emergency vehicles will be maintained.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends